Skip to Content
0
Former Member
Jul 09, 2015 at 02:14 PM

Unable to consume PIR in MD04 with Planning strategy 40

24 Views

Hi Experts ,

I have selected planning Strategy as 40 , then created PIR through MD61 of 30 nos. , then created demand through MD81 of 4 nos. , but at the time I enter the demand of 4 nos. then system should reduce PIR by 6 nos. but still it is shown as 10 in MD04 ,its not getting consumed please suggest

Attachments

Capture.JPG (51.6 kB)