on 07-09-2015 2:19 PM
Hello
I would like to know how heuristic would prioritize the below durations:
1) Transportation Duration Means of Transport section of Transportation lane
2) Planned Delivery Time maintained in Transportation Lane
3) Planned Delivery Time maintained in Material master
My understanding is:
Heuristic would first try to pick Transportation duration in Mean of transport. If that is not maintained, Heuristic would look for PDT in Transportation Lane. If it is not maintained, it would pick PDT from material master ?
I have read other posts, but if someone can confirm the behavior, it would be of great help.
Thank you
Aditya
Hi Aditya,
This thread explain very well your topic http://scn.sap.com/thread/3617307
Thanks,
Regards, Marius
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Aditya,
Try one scenario in your test environment. It will hardly take 20~30mins to check complete behavior by maintaining all and then removing one by one the PDT value from different sources and see the results.
Regards
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.