Hello all. I could not find a Time Sheet section, so I'm asking here in the PS area.

We are using CATS to do effort confirmation in our PS network activities and it is working fine, except for one small detail. The entry screen contains one full week, but whenever someone tries to post in the same line, same activity, effort in two days which are in different months(ex: 27.11.2015 and 01.12.2015), the system creates a new line to separate the confirmations, one in each month.

Anyone knows why SAP does this? I can't figure why.