FG planned order and SFG dependend requre and in different month

Feb 01, 2017 at 11:25 AM

67

avatar image
Former Member

Team,

Please check the below , FG planned order is created on 03.03.2017 and even planned order is creating in March ( I have converted planned order to PO) but DepReq is still in FEB

May I know why is it happening , I have updated lead time for FG & SFG30 days


10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

avatar image
Former Member Feb 01, 2017 at 12:43 PM
0

Hi Vijesh,

Did you run the MRP, after changing the planned order?

Best Regards

Venkat

Show 3 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Please help

0
Former Member

Hi Venkat,

even after i run the MRP , depend requirement still in past whereas planned order is creating for future

may i know why is it happening?

thanks

0
Former Member

Hi,

this is what showing in planned order, start date is showing as today is this the reason why depended requ.is creating in past though the FG PO is updated in future? thanks to help.

0
avatar image
Former Member Feb 01, 2017 at 01:49 PM
0

No , but may i know why the depend demand is generating in back dated without respecting FG date?