on 07-06-2015 8:32 AM
Hi Gurus,
I have created a work center with capacity category as 002. Scheduling formula SAP004 (other formula) and capacities formula SAP008 (other formula)
The work time is from 08:00 to 18:00 with break of 1 hour.
I am using this work center is service order. In the operation I gave total time as 2 hours and did scheduling.
After scheduling the start time was 08:00 and end time was 10:13:20.
Why the system is taking extra time of 00:13:20?
Regards,
Smart kumar
Hi Smart,
In the work centre, remove the break hours and test it.
Regards
Terence