In the environment of product cost collector with production order, product cost collector
have several production order with status ‘TECO’.
When we calculate WIP, WIP in a previous period is not canceled.
Our customer want to cancel WIP in a previous period for production order with status ‘TECO’.
Hi Big Choi,
Did you check the settings for RA Version, RA Key in OKG3.
Click on Expert Mode and you'll see Valuation methods per status.
Select the one for TECO and check the settings.
Cheers,
Szymon