on 07-01-2015 6:44 AM
Hi,
I am relatively new to PM module
I have a requirement like this...
Client procuring some machines. They have to carry out preventive maintenance based on following criteria...
Machine installed today. Now they need to carry out preventive maintenance based on following criteria..
1. after 1 month or reaching 100 hrs of machine run which ever is earlier
2. after 2 month or reaching 200 hrs of machine run which ever is earlier
3. after 3 month or reaching 300 hrs of machine run which ever is earlier
like the above it goes on...
We can not calculate the annual estimation of the machine as machines run one day only 1 hr and next day 8 hrs another day 3 hrs like this..
How to design this so that we get preventive maintenance orders automatically when we we run IP30 deadline monitoring..
Thanks
Kumar
Hi Kumar,
In order comsider 2 Unit ( Month and Machine Run) for scheduling create cycle set -ip11z
Also if you want to your plan to work effectively for Mcahine Run you need to give correct Annual estimate. if not you can use exit which Intern will update annual estimate evry time when you post new Maesuring document.
exit -MEASURE_POINT_UPD_PYEAR
Link - Optimizing the Scheduling - Maintenance Planning (CS-AG/PM-PRM-MP) - SAP Library
Rgds
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kumar,
As such Field is not Mandatory while you create Measuring Poin ( with Counter Tick On), but definitely there dependecy of schedule on Annual estimate.
F1 help-
Annual estimate for the object to which the counter applies
This field is used in conjunction with maintenance plans in regular maintenance to calculate the necessary maintenance intervals (counter-based maintenance).
Rgds
Sunil