on 06-30-2015 8:30 AM
Team,
i have a requirement to manually create an inspection plan for an inspection lot. i have created an inspection plan through QP01. the issue is, when i try to assign it the inspection lot through qa02, i am getting the error Inspection plan not found. what could be the issue?
The Usage is 5
Inspection lot origin is 08(Stock Transfer)
Inspection type 08
Hi,
Check the Inspection plan Usage & status (QP02) with repsect to inspection type-08
Note ;change the Insp.plan Usage from 5 to 9 & status-4 then it will work.
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ok! Check below link if proves useful! I have tried clubbing possible reasons and solutions for this.
http://wiki.scn.sap.com/wiki/display/PLM/Inspection+lots+with+CRTD+status-+Causes+and+Remedies
Anand
Hi Mutale,
Please check your Inspection valid from date which was created after inspection lot generation. Now delete the inspection plan and create new inspection plan, in which change valid from date which should be earlier than inspection lot creation. Now in QA02 assign inspection plan. Pl reward points if it works.
Thanks.
B. Chowdhury
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.