on 06-30-2015 8:50 AM
Hello Experts,
Can we transfer budget from one cost element to other with in same wbs element .
Please tell me how to do that .
Regards
Amit
Hi Amit,
How are you doing budgeting at the cost element level?? It is not available in SAP PS..
Regards
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Amit,
As mentioned by Paulo, this can be achieved using FM budget controls. You need to evaluate which budgeting controls you want to be active for your projects and procurement ( directly and via projects)..
you need to take help from your FICO colleagues to achieve it.. Not covered under PS domain..
Regards
Sammar