Hello Experts,

Can we transfer budget from one cost element to other with in same wbs element .

Please tell me how to do that .

Regards

Amit

Accepted Solutions (0)

Answers (1)

Answers (1)

sammar81
Employee
Employee
0 Kudos

Hi Amit,

How are you doing budgeting at the cost element level?? It is not available in SAP PS..

Regards

Sammar

former_member191210
Participant
0 Kudos

This message was moderated.

Paulo_Vitoriano
Active Contributor
0 Kudos

Hi Amit,

Budgetting at account level is available in the Funds Management (FI-FM), but that is quite a big module to implement (if not on the functionality, but mostly on processes and procedures).

Regards,

Paulo

sammar81
Employee
Employee
0 Kudos

Hi Amit,

As mentioned by Paulo, this can be achieved using FM budget controls. You need to evaluate which budgeting controls you want to be active for your projects and procurement ( directly and via projects)..

you need to take help from your FICO colleagues to achieve it.. Not covered under PS domain..

Regards

Sammar