on 06-26-2015 4:00 PM
Dear Gurus,
We have the 2 company codes out of 2 we have done the configuration for 1 company code in OB22 ran the depreciation since 2011 t0 2013 now we want to run the depreciation which is assigned in OB22 but system giving the bellow error.
1000-Not assigned in OB22
1001-Assigned and ran the depreciation upto 2013.
Now when we try to run the depreciation system through error msg.
In OB22
Hi Mahi,
Create a new depreciation area for parallel currencies in OADB. Later you have to define adoption values for APC costs & depreciation terms from area 01 in OABC & OABD. Later you have to do parallel currencies configuration for the new dep.area. For configuration go through the below link:
Regards,
Mukthar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This could be a program bug. Check the OSS note http://service.sap.com/sap/support/notes/1953617 , if applicable for you release.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.