Hi all,

I am facing problem while taking the database backup which is taking lot of time. To avoid this i want to change the value of Parallel execution in BRTOOLS but i am not getting the correct way to do it.

Plz help.

Thanks,

Rajat

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

avatar image
Former Member Feb 01, 2017 at 10:36 PM
0
Share
10 |10000 characters needed characters left characters exceeded
James Zhang
Feb 02, 2017 at 07:03 AM
0

Hi Rajat,

brbackup -e option can be used, for the details, please check:

http://help.sap.com/SAPHELP_nwpi711/helpdata/en/47/1f0e15943a4403e10000000a1553f6/content.htm

Best regards,
James

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Feb 13, 2017 at 11:21 AM
0

Hi ,

Thanks for the help. The issue is solved now.

Regards,

Rajat