Hello,
As This is my first post on this forum I would like to say Hello to everyone and wish best of luck. I hope I will explain my problem well.
I have a question related to re-costing.
The Sales Order costing is done. The Production Order & costing is done. The production has started. During the production on 1st WC we realized that there is missing item in BOM. We would like to correct that and re work the BOM, re-cost the Sales order and than go to Prod Order. But I would like to see the changes not in Prod Variance but in Prod Order costing. So in the cost of Prod Order in summary on prod papers.
Is it possible to re-cost sales order in that way that it could impact the prod order costing without creating new prod order etc?
If I didn't explain it properly please correct me.
Regards,
Wojtek