on 06-22-2015 10:57 AM
Hello ,
It will be really helpful to answer theses questions :
-Is there any specified field where I can enter the capacity of a work center for example 1000 piece/ H ?
-Can you give me an example of formula for calculating capacity requirements of a work center ?
Thanks .
Hello Marouane,
1 - This is mentioned in routing but not in work center. Work center defines total capacity. In routing (CA01/02) you define usage of that capacity. So total capacity is 8hours and 1000p/hour would be defined in routing which will consider this.
2 - Formula - SAP002 - Machine * Operation quantity / Base quantity. Example you have maintained 1000p/hr in routing so base is 1000pcs. Now if you have a production order for 10000, then system would calculate this way:
1hr * 10000pcs / 1000pcs = 10hrs
So we need 10hrs to produce 10K pcs.
I hope its clear for yourself.
Regards
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.