Min Lot size

giuseppe_conte
Explorer
0 Kudos

Hi,

I have a production order for 54, however, the component can only be ordered in multiple of 10s, so I need to set up the material master for the component in order to get the MRP to create a requisition for 60 rather than 54.

I have set up the rounding value of the component to 10, and the minimum lot size too, however, everytime I run the MRP, it creates the Purchase requisition for 54

can you please help?

thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

RahulHanda
Active Contributor
0 Kudos

Hi Giuseppe

What is the lot size maintained in material master, MRP1 tab? It should be EX. What's the minimum lot size you have maintained?

Regards

Rahul

giuseppe_conte
Explorer
0 Kudos

Hi Rahul,

     yes it's EX..

I need a minimum of 10, as I am only allowed to order from my supplier in multiple of 10s.

thanks

RahulHanda
Active Contributor
0 Kudos

Giuseppe,

Check in OMI4, no one has ticked "Last lot Exact" for EX itself. I hope you are not using rounding profiles

Regards

Rahul

giuseppe_conte
Explorer
0 Kudos

sadly,

no access to OMI4

we've purchased this part in the past without restriction, only recently the supplier has added a minimum lot size.

I thought adding the rounding values and the min lot size, I'd have driven the MRP to order in multiple of 10s and min. of 10s..

is there anything else I need to do on the MM?

RahulHanda
Active Contributor
0 Kudos

Just remove minimum lot size and take a MRP run with rounding value. For above setting check with your IT to cross check the setting in OMI4.

Also check in info record if you have maintained minimum quantity which is contradicting with rounding value.

Regards

Rahul

saurav_sarkar3
Active Contributor
0 Kudos

Try using the Fixed Lot Size with Lot-procedure EX

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Please read carefully the following note, where the system behavior is described in more detail:

49663MRP: Rounding and minimum/maximum quantity

According to this note, If the minimum quantity is not a multiple of the rounding value, the rounding value is ignored when creating order proposals for requirements that are smaller than the minimum lot size.

Therefore, the solution to this issue is very simple, you should maintain a minimum lot size of 60, as this is a multiple of the rounding value 10.

BR
Caetano