DP93- Error " No Expenditure Item found" ( DIP profile - Source 1005- inter company line items)

Hello,

I am getting an error message " No Expenditure Item found" when running the RRB using DP93.

Here is the scenario:

1. Project and top level WBS created in CC 1000. This is billed to end customer.

2. A level 2 WBS element is created in CC 2000, assigned with inter-company customer. ( I have done the inter-company configuration like assigning the customer to co.cd)

3. A sales document type PS1 created in CC 2000 and a DIP profile added which has the source ( 1005- Inter-company line items). The DIP profile Config is created with Source 1005 and selection criteria - cost elements & activity type. A material determination is used to item the cost.

4. Actual costs are captured using network activities assigned to level 2 WBS in CC2000.

5. I Ran the DP93 for the Sales document. I end up getting the error " No Expenditure Item found".

Let me know if I have followed the ICRRB process and if you have any answers to overcome the error.

sales-doc.jpg (122.5 kB)
dip-profile.jpg (111.8 kB)
dip-profile1.jpg (134.7 kB)
error.jpg (236.7 kB)
project-str.jpg (69.8 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Feb 01, 2017 at 05:32 AM

    Hello,

    Check your settings in the DIP profile. This error message is usually shown, when the costs cannot be found by the system due to the
    settings in your DIP profile.

    You can follow the analysis described in SAP note 1120767.

    Regards,

    David

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 01, 2017 at 04:04 PM

    Thanks David. I looked at the note.

    As suggested in note, I have the actual costs that shows up in ps cji3 reports. And I have not selected the flag "process dyn items with material only".

    There is also a mention about debuging the function module, but i could not get a clear direction. I am checking wirh my technical team.

    I have a question for u. For the source 1005, will the actual cost be picked like the source 0001?? Or 1005 has a spl process for picking the cost?

    Add comment
    10|10000 characters needed characters exceeded