on 06-16-2015 2:47 PM
Hi experts,
how could I manage to determine a baseline date 45 days plus document date?
I can only set months and fixed days, but I need to add a number of days.
I have tried setting 45 No. of days and percentage "100%" but the system does not accept a percentage of 100%.
I have also tried with a substitution (previously I've set BSEG-ZFBDT as a substitutable field in GB01) but it does not work.
How could I get that?
Thank you very much,
Nadia.
Hi Nadia,
Its Simple.Create Payment Term with 1. Document Date as Baseline Date and 2. Days as 45 without any percent.
It will solve your problem.
Warmest Regards
Vineet Lodha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nadia,
Do You need the display of Payment Term description or Due date on SD Invoice Smartform ?
Payment Terms generally work in both FI and SD module in similar fashion.
I personally do not believe and recommend making calculations in SmartForm unless unavoidable.
Warmest Regards
Vineet Lodha