Help needed regarding Minimum Passing amount in Continuos IO peggng

Former Member
0 Kudos

Hi Team,

        In Continuous IO Pegging, I have defined a Minimum Passing Amount of 100. So, the Planned Orders created should have a minimum value of 100. But, the Planned Orders are created with a value<100.

Please let me know if there is any setting that is affecting my expected result.

Thanks in advance for the help.

Thanks & Regards,

krovvi.

Accepted Solutions (1)

Accepted Solutions (1)

RahulHanda
Active Contributor
0 Kudos

Hi Krovvi,

I hope you activated the business function SCM_APO_PPDS_PI. Please got through the below link to see if you are not missing anything.

Optimizer Planning for Continuous I/O Nodes - Production Planning and Detailed Scheduling (PP/DS) - ...

Planning of Standard Lots for Conti I/O # Minimum Passing Amount - Production Planning and Detailed ...

Also check SAP note

1533835 - Continuous material flow in PP/DS optimization

Regards

Rahul

Message was edited by: Rahul Handa

Message was edited by: Rahul Handa

Former Member
0 Kudos

Hi Rahul,

    Thanks for the help. The issue has been resolved now.

Thanks & Regards,

Srikanth.