Hi,

Subcontracting process integration with SNC.

We have done the work order configuration as per the standard config document.

We have maintained RT Consumption tick in Info Record, Work order is created in SNC and are able to process the phases in work order.

When I update the work order with Yield, Scrap qty in production log, the XML (ManufacturingWorkOrderProductionProgressNotification_Out) gets generated and the same is send to ECC. XML is success in ECC

The problem is the data is not getting updated in ECC. Component Consumption data is not updated based on the XML. ME2COMP & ME2SCRAP report are not updated.

Let me know if there are any additional config that needs to be done to get the consumption data updated in ECC.

Thanks,

Harshad M.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    May 06, 2016 at 07:40 PM

    Hi Harshad

    Did you discover how these t-codes are update?