Resource displayed in SNP Planned Order

Dear Guru,

I have a SNP PDS which has 3 operations, each one will have a different resources, which resource should be displayed in the SNP planned order? The 1st or 3rd, or there are some settings I can do to change it?

Please kindly help!

BR,

Lawrence

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    Jun 03, 2015 at 10:15 AM

    Hi Yang,

    It will take the third, as this would be giving final output for this product. In RRP3 you would see the 3rd one.

    Regards

    Rahul