Budgeting on only Fund centre

Hi Experts,

Is it possible to have budget only on Fund Centre instead of Fund centre and commitment item. Currently we have Fund Centre + Commitment item budgeting. Now we want to change to Fund Centre only.

Is it possible.

Please guide.

Regards

Zunaid

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Jun 03, 2015 at 12:27 PM

    Zunaid,

    I believe this is not possible. You can, however, have a single default commitment item.

    Thanks

    Shyam

    Add comment
    10|10000 characters needed characters exceeded

  • Jun 03, 2015 at 06:07 PM

    Dear Zunaid,

    Beside thinking SAP for a while, it is not logical as well as practical to do budgeting on the basis of just Funds Centre/Department. You have to keep budget on budget heads (Commitment Items), such as Salaries, Supplies, Travelling Expenses etc.

    In standard it is not possible to do budgeting without CI. The system will ask you for CI and FC on every financial transaction.

    Regards,

    Amar Lal

    Add comment
    10|10000 characters needed characters exceeded

  • Jun 04, 2015 at 05:35 AM

    Thank you so much guys