Is it possible create a project in PS in specific decision point in PPM?

For example: Should be create a project in PS automatic when determine phase in PPM is closed.

I'm not finding a specific documentation on the subject.

I used o subject - Defining Settings for Assigning an Item to a PS (page 83) - from documentation: (Documentation ConfigContPPM60SP01).

Does anyone know if this is possible?

Thank you so much.

Lilian Amélia Pereira

Accepted Solutions (0)

Answers (2)

Answers (2)

ashwinipingle
Participant
0 Kudos

Hello Lilian,

Did you find a way to automate the PS project creation when a particular phase of PPM is closed?

Probably even I will need to do similar functionality so in case you have additional info on this-  please help.

Regds,

Ashwini Pingle

Former Member
0 Kudos

Hello Ashwini,

No, I didn't. If you find something, share with me too.


Regards,
Lilian Amélia Pereira

mariano_sabiche
Active Participant
0 Kudos

Hello Lilian;

There are one solution to this, and it's creating the PS Project in the first decision point approval status. At SAP PPM 6.0.

Best regards,

Mariano

Former Member
0 Kudos

Hello Mariano,

OK, I wish it were possible create project in PS in the last decision point approval.

Thank you for answer.

Lilian Amélia

mariano_sabiche
Active Participant
0 Kudos

Hello Lilian;

I think that it's not possible to create at standard way in the last decision point approval. You will have to do an enhancement for this and if you want it automatically too.

Hope this would help you.

Best regards,

Mariano

ashwinipingle
Participant
0 Kudos

Thanks a lot Mariano. This helps a lot!!

mariano_sabiche
Active Participant
0 Kudos

Hello Lilian;

Did you solved this issue?

Points will be helpful.

Best regards,

Mariano

former_member188458
Active Participant
0 Kudos

Hi Lilian ,

There is no Out of the box SAP std functionality .

However you can do custom enhancements to auto generate a Project on Phase closure.

Best Regards,

Rini