on 06-02-2015 4:14 PM
Hi all,
I have a very weird behaivour. I have activated MRP for a plant and in a material i have define V1 as MRP run and HB as lot size (replenish to maximum stock). I upload stock with 561 movement type and then i run MRP. However, the MD03 does not show the available stock (it shows zero - 0 ) and it creates a PR for the total quantity it needs to go from zero stock to the maximum stock.
In addition, if i double click at MD04 result at the 1st line where the stock is zero, it shows as untrestricted quantity 4, which is the quantity i have in stock!!!
any ideas?
BR
Hello
Check if BAdI MD_CHANGE_MRP_DATA is implemented, as this is very often used to manipulate the stocks.
In addition, check if the storage location where the goods movement was posted is relevant to MRP or if it belongs to any MRP area.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi all, BAdI MD_CHANGE_MRP_DATA was activated and manipulated the results. case closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi both,
Rahul i do not have SAP Hana on the system. Caetano, the st. location does not belong to any MRP area. But what about it's relevance to MRP? the plant is relevant to MRP.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ali,
Not sure if you have activated HANA optimization in MRP. If yes cross below SAP note. Though still check whether all views in material master are active.
1970796 - SAP HANA: Planning result returns empty list without stock line
Regards
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.