Hi there,

We are using backward scheduling for all our Production order types. We have created standard routing also that flows into Production Order.

I have following doubts.

1) If Production Order is created with backward scheduling option. It is observed 2 out of 10 operations are confirmed. At this point of time can I change the back ward scheduling to Forward scheduling?

2) If I change scheduling type to Forward scheduling whether operation start date and finish date will change automatically as per time maintained in operation?

If we can do above 2 how to do it?

What changes in configuration are required?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jun 02, 2015 at 06:21 PM

    Hello

    Please observe that, when an operation is confirmed, the confirmed dates are considered during the scheduling of an order and the scheduling follow the option defined on the order header. There is no setting to change that on the standard system.

    BR
    Caetano