Equipment Breakdown to be reflected in PP capacity planning & locking respective PP Work center.

0 Kudos

Dear PM Gurus,

My client has one requirement that, whenever a breakdown notification/order is created in system it should be reflected in PP Capacity planning and no production order can be processed using that work center.

I have done the same configuration for preventive maintenance through standard but couldn't achieve for breakdown!

Is there any standard way to achieve this for breakdown?

Thanks in advance!

With Warm Regards,

Shivkumar Tiwari

Accepted Solutions (1)

Accepted Solutions (1)

former_member201392
Active Participant
0 Kudos

Hi.. Shivkumar,

as per your requirement you have to do the  below :-

1. Maintain the PP Work Center in Equipment >> Location Tab>>Work Center.

2. When you Create Breakdown Maintenance Order Select System Condition Should be "0" not in Operation.

>>> after selecting this , work Center capacity consumed against the Maintenance order.

3. run TCode :- CM25 you can see the Work Order with consumed capacity.

0 Kudos

Dear Lokesh,

Thanks for the reply, I have tried as you said but breakdown is not reflecting in CM25 of the work center.

I have done following :

Maintained PP work center in location tab of equipment

Created breakdown maintenance order w.r.t to notification,

Maintained breakdown tick in order and system condition to '0' Not in operation,

Released the order & Saved,

Ran tcode CM25 & CM21 it was not reflected in any of the tcode.

Did i missed something or there is any configuration which i missed?

Kindly reply,

Regards,

Shiv

sunil_mundhe3
Contributor
0 Kudos

selection in CM25 should be PP work centre and Plant.

Please check Profile which you are selecting while executing CM25.

Rgds,

Sunil

0 Kudos

Dear Sunil,

I have entered PP work center and plant in CM25 & the profile is SAPCRPG001 and tried few more profiles still cannot get it in CM25. If you know which profile to use for PM orders to be included in CM25 kindly reply back.

Thanks & Regards,

Shiv

former_member201392
Active Participant
0 Kudos

Hi... Shivkumar,

at the time of running the Tcode :- CM25

enter Over all Profile :- SAPCRPG002 

, provide your work center (which you assigned earlier in Equipment master location tab) &  plant.

after that execute the same. 

you can analysis the work center capacity....

sunil_mundhe3
Contributor
0 Kudos

Hi Shiv,

I Have tried SAPCRPG001 & SAPCRPG002 and PM order is shown in both profile selection.

Not sure whether any one changed profile in your system?

Rgds

Sunil

Former Member
0 Kudos

Shiv,

What formulae do you have assigned to the PP work center (IR02, tab "Capacities")?

Paul

S0022314014
Active Contributor
0 Kudos

Sunil

Share with us, the screen shot of the strategy profile from CM21 - Menu --> Settings --> Strategy

regards

Savas

sunil_mundhe3
Contributor
0 Kudos

Hi Shiv,

Please share..

Answers (3)

Answers (3)

0 Kudos

Thanks a lot everyone for you replies it does reflect in CM25.

Actually while testing before i did not put work hours required to complete the job, because of which it was not reflecting in planning chart.

After maintaining the work hours in order and capacity formula in work center, everything is working fine.

Thanks to you all again for all your replies !!!

Regards,

Shiv

former_member201392
Active Participant
0 Kudos

Hi..shiv

please share the screen shot ....

sunil_mundhe3
Contributor
0 Kudos

Hi Shivkumar,

Create work center and assign it to equipment location tab work center.

When you check capacity for work center it reflect in planning board.

We tried this for planned maintenance not sure abt b/ d maintenance.

0 Kudos

Dear Sunil,

Thanks for the reply but I have done it for Planned maintenance I want to do the same for breakdown maintenance.

Regards,

Shiv