work center capacity levelling

former_member822355
Participant
0 Kudos

I have un set of material, with a very simple production, one operation, one route. Imagine this situation. Material M1 , could be produced in the work center C1 or alternative in the work C2: the are two different work center, but they can produce M1 in the same way. Material M2 could be produced in work center C1 and C3 Material M3 could be produced in work center C3. Imagine that C1 is loaded at 130% and C2 is load only ad 30%., C3 is loaded at 40%. How can I setup materials, work center, routing in order to obtain an automatic leveling between work centers.. I mean, I would like that sap automatically recognize that C1 is loaded at 130% and switch part ofM1 production to C2or switch part of M2 production to C3. Keep in mind that the production process is very simple, one operation, one route. Thank you very much.

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Silvana

I suggest you to create two different production versions, one for each work center.

After that, on the strategy profile used for capacity leveling, you should select the option "Change production version on error". That way, system will dispatch the orders for the first work center, until finding an overload. When it finds an overload, an error is triggered and system tries to change the production version and dispatch to another work center.

BR
Caetano

former_member822355
Participant
0 Kudos

Could you explain me with print screen and examples? Thank

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Silvana

I don't have any step-by-step of this scenario.

It's just the creation of production versions and checking a flag on the strategy profile.

I believe that you can do that by yourself and test this scenario.

Come back if you have more specific questions during your tests.

BR
Caetano

former_member822355
Participant
0 Kudos

I tried to do it. But I have some problems.  Here is cm25 before dispatch.

And material C4151 has product version as you can see in the next image

Group 5000000007 is associated to work center GOGLIO45.

After dispatching in CM25 I have the following situation:

I don't like it. I want that order 31261 is left on 3.6.2015 and put on work center GOGLIO45. Why dispatch change the date and do not use production version?

strategy is the following:

opu5 is set like this:

Answers (1)

Answers (1)

RahulHanda
Active Contributor
0 Kudos

Hi Silvana,

You need to use alternative sequencing in this case. Go through the link which would explain how to set this. You can set the same for your materials.

Hope it answers your question.

Regards

Rahul

ahmed_talaat
Discoverer
0 Kudos
please elaborate