issue in demand flow to alternative BOM selection in sales order

58 Views

Hello All,

I have two alternative BOM 01 and 02 with usage-3 Universal. I am manually selecting alternative BOM (02) at sales order creation. when i run MRP, Planned order is generated for the sales order but alternative BOM 01 is picked in the planned order. I need the alternative BOM which is selected at sales order creation to flow in the planned order.

I have maintained following parameters in the material master:

  • MRP type - PD, lot size-EX, No Fixed lot size, Procurement type-E, Strategy group-20, availability check-02, BOM selection method- Selection by order quant.

Kindly help me out to overcome this issue

Regards,

Manoj