on 05-28-2015 3:33 PM
Need to use multiple counter for
Every 100 hours
Every 1 Month
Created Cycle set used in Maintenance Plan (IP43)
1 .For the above created Characteristics Hourly and Month.
2. Then Create measuring point for both Hourly and Month
3. Did initial Entries for both measuring point
5 Hours
1 Month
4. Schedule the call IP10.
5. IP30 Order get generated on the basis of Month Next i tried to create order on the basis of Hours and created document up to 200 Hrs but order not get generated..
Please let me know the issue..or explain step by step to take ......
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Greetings Devesh,
Please consider your Annual Estimates on the particular Counters.The planned dates are determined based off those.
See more info in this document posted by Rakesh Mane.
Hi,
Firstly activate as Enhancement Multiple Counter Plan according to suggested by savas.
and find go through as below link.
Multiple Counter Plan - Maintenance Planning (CS-AG/PM-PRM-MP) - SAP Library
Cycle Set Sequence in Multiple Counter Plan - Maintenance Planning - SAP Library
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.