Multiple Counter

25 Views

Need to use multiple counter for

Every 100 hours

Every 1 Month

Created Cycle set used in Maintenance Plan (IP43)

1 .For the above created Characteristics Hourly and Month.

2. Then Create measuring point for both Hourly and Month

3. Did initial Entries for both measuring point

5 Hours

1 Month

4. Schedule the call IP10.

5. IP30 Order get generated on the basis of Month Next i tried to create order on the basis of Hours and created document up to 200 Hrs but order not get generated..

Please let me know the issue..or explain step by step to take ......