Budget check

Hi,

We have activated strict budgetary control in the middle of the year. Many purchase requisitions are created before strict budgetary control and there was no budget. Now even after activating strict budgetary control, system is permitting Purchase order, MIGO and MIRO document. if there is increase in value it will give error message. But with same value system is permitting subsequent documents

Lincy

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    May 28, 2015 at 12:37 PM

    Hi,

    What setting you had before applying strict control? Please, notice that MIGO is not supposed to trigger AVC checks + it depends on the settings you made in your update profile in OFUP.

    Regards,


    Eli

    P.S. In any case, I'd suggest initializing AVC ledger via FMAVCREINIT since you have changed a core setting in AVC configuration.