Dear All,

We have a requirement from the users to have scheduling like this.

For example, we have 3 Planned Order, A, B, and C.

All of them use same work center.

A is scheduled from Day 1 - 10

B is scheduled from Day 11 - 20

C is scheduled from Day 21 - 30

if A is now changed to be scheduled from Day 1 - 9, then B can be adjusted automatically to Day 10 - 19, and C to Day 20 - 29.

Is there any way to do this in SAP?

Appreciate your comment and feedback.

Useful reply will be rewarded.

Thanks,

Steve