Dear All,
We have a requirement from the users to have scheduling like this.
For example, we have 3 Planned Order, A, B, and C.
All of them use same work center.
A is scheduled from Day 1 - 10
B is scheduled from Day 11 - 20
C is scheduled from Day 21 - 30
if A is now changed to be scheduled from Day 1 - 9, then B can be adjusted automatically to Day 10 - 19, and C to Day 20 - 29.
Is there any way to do this in SAP?
Appreciate your comment and feedback.
Useful reply will be rewarded.
Thanks,
Steve