Commitment value not populating in reports

Hi All,

I have created a PO with account assignment "P" for corresponding WBS, I am not able see the commitment value in any of the commitment reports.

What can be the reason and what are the setting to be enabled .

Thanks and regards,

GVK

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

6 Answers

  • May 27, 2015 at 08:40 AM

    Hi All,

    I have checked in OKKP the commitment management is active and also I have tried to check reports in cje0 and cji5, I am not able to get the Quantity as well as Value of the commitment.

    Regards,

    GVK

    Add comment
    10|10000 characters needed characters exceeded

  • May 27, 2015 at 04:39 AM

    Dear,

    Is Your WBS element is having status AVAC Availability control active?

    Did you check the report CJE0?

    If every thing is fine but still facing problem with commitments,

    First run report : RKANBU01 which will update PR/PO commitments for projects

    Second run report RKACOR04  which will update entries in table  like COSP, COSS,COEP, COOI.


    after these steps run CJEN transaction to reconstruct  the all the budget related activities for the given project. This transaction can be executed in "Test mode" also.


    then run CJBN transaction to reconstruct availability controls for given project.

    If still having problem ,kindly share the screens.

    Regards,

    Pardhu

    Add comment
    10|10000 characters needed characters exceeded

  • May 27, 2015 at 05:53 AM

    Hi,

    Can you please brief what reports you have checked ?

    In Simple did you check in CJI5.

    Please provide some screenshots

    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 27, 2015 at 06:32 AM

    Hi

    the below notes would be useful

    152571 - Composite SAP note: Missing or incorrect commitments

    47992 - No commitment is displayed in reporting

    Also check whether  commitment management is activated or not  against controlling area ,fiscal year in t code OKKP

    Regards

    Vijay kumar Hebbal

    Add comment
    10|10000 characters needed characters exceeded

  • May 27, 2015 at 01:32 PM

    Hi All,

    I was able to solve the issue. Thank you all for your time.

    I had to tick the Project and w.commit checkbox in OKKP. I had tried this earlier before posting my query but it dint work as there was some issue in the dev system , it was working fine in Q system , the value is getting reflected in all the slr and cje0 commitment report but not in cji5 report in Q system.

    regards,

    GVK

    Add comment
    10|10000 characters needed characters exceeded

  • 18 hours ago

    Than you tik as answered, it will be easy to use it by looking answered

    Add comment