Hi All,

I have created a PO with account assignment "P" for corresponding WBS, I am not able see the commitment value in any of the commitment reports.

What can be the reason and what are the setting to be enabled .

Thanks and regards,

GVK

Accepted Solutions (0)

Answers (6)

Answers (6)

Former Member

Hi All,

I have checked in OKKP the commitment management is active and also I have tried to check reports in cje0 and cji5, I am not able to get the Quantity as well as Value of the commitment.

Regards,

GVK

MTerence
Active Contributor
0 Kudos

Hi,

Is this issue occurs for all projects or this is just for one project.

Regards

Terence

Former Member
0 Kudos

Hi Maria,

This issue is occurring for all the projects.

Thanks and regards

GVK

hemu_katta
Participant
0 Kudos

Than you tik as answered, it will be easy to use it by looking answered

Former Member
0 Kudos

Hi All,

I was able to solve the issue. Thank you all for your time.

I had to tick the Project and w.commit checkbox in OKKP. I had tried this earlier before posting my query but it dint work as there was some issue in the dev system , it was working fine in Q system , the value is getting reflected in all the slr and cje0 commitment report but not in cji5 report in Q system.

regards,

GVK

Former Member
0 Kudos

Hi

the below notes would be useful

152571 - Composite SAP note: Missing or incorrect commitments

47992 - No commitment is displayed in reporting

Also check whether  commitment management is activated or not  against controlling area ,fiscal year in t code OKKP

Regards

Vijay kumar Hebbal

MTerence
Active Contributor
0 Kudos

Hi,

Can you please brief what reports you have checked ?

In Simple did you check in CJI5.

Please provide some screenshots

Regards

Terence

pardhreddyc
Active Contributor
0 Kudos

Dear,

Is Your WBS element is having status AVAC Availability control active?

Did you check the report CJE0?

If every thing is fine but still facing problem with commitments,

First run report : RKANBU01 which will update PR/PO commitments for projects

Second run report RKACOR04  which will update entries in table  like COSP, COSS,COEP, COOI.


after these steps run CJEN transaction to reconstruct  the all the budget related activities for the given project. This transaction can be executed in "Test mode" also.


then run CJBN transaction to reconstruct availability controls for given project.

If still having problem ,kindly share the screens.