Hi Experts,

Please suggest me the right way for:

I have a separate inventory plant 2001,when i create a production order in production plant-2002 then generate a reservation slip with 301 mov.type for required material & qty.

for example: i have 100 qty of RM1 in plant 2001.

                 

In plant 2002 production component is RM1 & qty 10 then now i want to reserve this 10 qty for this 2002 plant and if i generate a new reservation for same material RM1 qty 100 for  next plant 2003 and when i go to transfer the stock for plant 2003 then system should not be allowed.

So please guide me,is it possible with any process/customization/settings/enhancement.

Thanks & Regards,

Vivek Bhojak

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • May 23, 2015 at 08:50 PM

    Hi Vivek,

    Basically conclusion is, if you have reservation slip of 10 (assuming you are doing the same in MB21) then system should not allow another reservation slip of 100 as total stock is 100.

    If this is the case then go in OMCQ and set error against message M7 181. This will not allow you to create reservation slip itself as stock is less.

    Let me know if it helped.

    Regards

    Rahul

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 23, 2015 at 04:12 PM

    Vivek,

    Your process flow is not entirely clear.

    How are the reservations in 2001 created?  Are these created automatically during the creation of the production order in 2002, or are you using some type of additional step?  Are you using a Special Procurement key in 2002?

    How does the material move from plant 2001 to 2002?

    Does the material move from plant 2001 to 2003, in the same way as it does for plant 2002?  If so, how?

    Best Regards,

    DB49

    Add comment
    10|10000 characters needed characters exceeded

  • May 23, 2015 at 05:51 PM

    Dear,

    I got your point.You want system should restrict user when he plans to create a reservation for 10qty in 2003 plant ,which he was already got from 2001 for 2002 plant production and made reservation for 10 qty out of 100 in 2002 plant.

    Kindly check the availability control parameters in SPRO-->IMG-->Material management-->Inventorymanagement&Physical inventory-->reservations-->set dyanmic availability chcek

    Are using single step or two step method?

    Regards,

    Pardhu


    pastedImage_0.png (57.3 kB)
    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Pardhu,

      I want to restrict to user in below condition:

      suppose available stock is 100,1st user create a reservation of 10 qty. then it will reserve .now user create a 2nd reservation for 100 qty.then it should not allow because 10 is reserved out of 100.

      i checked with this above checking rule but not got the expected result.

      if anything is possible in standard then please suggest me.

      BR,

      Vivek