What is the Z3 - MRP, fix type 3 sent to APO

Can some please explain about this MRP type in SAP ?

Thank you

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Feb 01, 2017 at 10:21 PM

    Hi Danny,

    All materials can be integrated to APO, regardless of MRP Type.

    If the MRP Type specified has Planning Method '1', it is to be planned in APO. If the Planning Method is blank or '2', the Location-Product will have Procurement Type 'P' in APO and will be integrated mostly for display purposes.

    Most likely, Z3 is a custom MRP Type created by your business for a specific scenario. You may ask under tag MAN Production Planning (PP) what it can be used for, if required.

    Regards,
    Tiago

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 06, 2017 at 06:33 PM

    thank you Tiago for the information.