Confirmation Unit of Work in Minutes

I am seeing random table entries into table AFRU that is in minutes when the confirmation is is hours. What would cause this?

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    May 20, 2015 at 05:07 PM

    Please check this thread for the solution:

    http://scn.sap.com/thread/3708363

    The actual work field on a confirmation can only accept one decimal place. If you enter a number with two decimal places, it converts the value to minutes when it stores it in the table.

    Paul

    Add comment
    10|10000 characters needed characters exceeded

    • Thanks Paul! This was the problem. I was trying to create a BOBJ Webi report and BOBJ brought in the confirmations in Minutes, not hours. So I had to create a variable to correct this.

      In case anyone needs it:

      =Sum(If([Uom Id Work Actual]InList("MIN";"STD");[SVC CONF - Qty Work Actual]/60;[SVC CONF - Qty Work Actual]))

  • May 20, 2015 at 04:51 PM

    This might be due to the Unit maintained for Work in Operations tab of the Order.

    Add comment
    10|10000 characters needed characters exceeded

  • May 20, 2015 at 04:58 PM

    Dear,

    what is the base unit of measurement capacit mentioned in workcenter.and capacity utilization unit in workcenter master.

    REgards

    PArdhu