Past consumption based planning

Former Member
0 Kudos

Once in a month, we check SAP stock level and past consumption data to determine what to buy and how much to buy, we then ask supplier to confirm optimal quantities for one container. Lead time is always 3 months. Product type: trading product.

I would like to know is there any way we can do this kind of planning in SAP and how to implement?

Accepted Solutions (0)

Answers (2)

Answers (2)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Please refer useful SAP help link,

Reorder Point Planning - Consumption-Based Planning (MM-CBP) - SAP Library

Best Regards,

R.Brahmankar

Former Member
0 Kudos

you can  implement /run   MRP with reorder  level and  max stock level  on every  month

for lead time , go through the below link