Hi all,

in upcoming days i am going to work in the SAP PM and MM integration part.

i am new to this area.

can somebody pls explain briefly of PM and MM integration like the follows,

What is the purpose of integration,

What are the things to be done for integration btwn PM and MM

how can we measure the integration benifit btwn Pm and MM

thanks in advance

siva-V

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on May 20, 2015 at 11:45 AM

    Hi Siva,

    In simple terms your procurement is handled in MM.

    Through PM work order, you can select the materials from ware house, there is no special paper work required. System will select the item based on the availability in stores, else system can purpose by creating a PR / PO. This will be consumed under maintenance order.

    Material Reservation / PR / PO

    Service Purchase

    Bill of Materials

    Regards

    Terence

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on May 20, 2015 at 05:50 PM

    Dear,

    the main critical part for PM/MM integration is generating P.R for material or services required for maintenance activities.Here you need to specify the P.R document type should be used for P.Rs generating through maintenance order.And also you need to set up the movement types required for Consumption and reversal of goods against maintenance order.Then you need to set up the what type of materials can be assigned as a BOM for technical objects.

    Setting up P.R document type:

    SPRO--IMG--Plant maintenance &Customerservice--Maintenance and service processing--maintenance and service orders--general data--define accpunt assignment category.&document type for P.R

    Setting up BOM

    SPRO---IMG--plant maintenance &customerservice--masterdata in plantmaintenance &customerservice--bill of material

    you also need to set up availability check up for materilas when you assign materila in maintenance order

    SPRO--IMG--Plant maintenance &Customerservice--Maintenance and service processing--maintenance and service orders--Functions and Settings for Order Types--Availability Check for Material, PRTs, and Capacities


    Regards

    Pardhu

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.