Dear Experts

I am planning consumption based plan in sapapo .

My finished material is having 2 level BOM . I have maintained Mrp type as x0 Lot size as EX and reorder point for 2000 ,consumption mode 2 Backward consumption 10 Forward consumption 99 in mrp3 and I have cifed material to APO changes have been replicated in APO

When I am running planning heuristics sap-PP-007 .Planned order are not getting generated in correct order multiple planned order are getting generated .

And also charcterstics are missing while generating planned order like width length colour etc

How to over come this ??

Regards

Virender

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • May 19, 2015 at 02:49 PM

    Hi Virender,

    I hope you scenario is not from the below (as you mentioned width, colour etc.) as we cannot use this heuristic for reorder point planning;

    o For make-to-order production

    o For configurable products

    o In the quota arrangement heuristic

    o For planning product interchangeability

    (standard explanation from heuristic itself)

    Plus it doesn't consider various parameters (though I guess you are not using them):

    o Safety time

    o Safety stock

    o Target days' supply and safety days' supply

    o Maturation time

    o Use total receipts and Use total stock

    Note: Since existing requirements are not considered in reorder point planning, the algorithm may create procurement proposals with which too much or too little is procured, or procurement is too early.

    I would suggest you to go through the standard information for this heuristic and consider whether this will meet your business requirement.

    Let me know if it helped.

    Regards

    Rahul

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Virender,

      Not sure what do you mean by "not in sequence"? Could share with some screen shot with comparison with ECC.

      Example as per your data I expect 20K order in ECC starting with todays date and ending in future considering in-house time from material master (just as an example).

      Regards

      Rahul