We want to have physical inventory for 2 day in the month of september. How we can plan that no goods receipt or goods issue for delivery to be planned for these two days. Like it should be considered like weekend or holiday for that specifc plant. SO PO delivery date or outbound delivery picking date should not be physical inventory date.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

5 Answers

  • Best Answer
    May 19, 2015 at 08:37 PM

    without clear communication internally as well as externally to customers, vendors and your carriers you can't really assume that there will be nobody who is late or early and standing at your doors exact on these 2 days. And if they are coming from far away and it will cost you extra money if you send them away then you really think twice if you are doing that.

    Your vendors will not know that your plant has a shutdown (even it is not really needed as I explained in my blogs Physical Inventory is more than just SAP - Legal Background and Preparation

    and Physical Inventory is more than just SAP - Strategic counting

    just because you change your plant calendar.

    Even with a good communication you will usually face this situation that a few deliveries arrive or people want to pick-up some material.

    Add comment
    10|10000 characters needed characters exceeded

  • May 19, 2015 at 11:29 AM

    Dear,

    Hope those two days are not planned shut down as per your factory calender.

    In such situation you need to freeze the Goods receipts and issues for all the storage locations of your plant on those two days.

    For those two days create physical documents by activating "Freeze Book inventory" and "Posting block".

    Have done spro settings to freeze the storage location for book inventory balances?

    SPRO-->MATERIAL MANAGEMENT-->INVENTORY MANAGEMENT&PHYSICAL INVENTORY-->ALLO FREEZING OF BOOK INVNETORYBALANCE IN STORAGE LOCATION

    Hope this may help you.

    Regards,

    Pardhu

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 19, 2015 at 11:10 AM

    Hi Kiran,

    Try with Factory calendar mark the days as holidays.

    Regards

    Ravikumar.B

    Add comment
    10|10000 characters needed characters exceeded

  • May 19, 2015 at 11:58 AM

    Please shedule background job for according to factory calendar in SM35.

    Select all days except 2 days requirement. For more details please discuss with Basis guys.

    Add comment
    10|10000 characters needed characters exceeded

  • May 19, 2015 at 07:04 PM

    Hi,

    You may check the functionality of "freeze book inventory" and "posting block" in MI01, which can control the physical inventory even with running business. You may set up the configuration in OMBP. Also check the "adjust book inventory" option in OLMB - PI - Settings for PI.

    If you want the particular dates to be counted as a holiday, you have to maintain the same at factory calendar level, as already suggested by experts.