Hi All,

Can anyone help me on this. How to check whether open procurement proposal i.e - PO will be considered during MRP run for specific material or not ? Stock for the material is zero but PO of 30000 qty is reflecting in MD04 screen.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on May 19, 2015 at 06:25 AM

    Dear Nikkhil,

    MRP Concept will work based on MRP type / Lot size / planning strategy / Quota usage / Source list etc..i.e. if you are maintain the planning strategy 10 then system will consider the open planned orders (other than firm) / PR / PO and open stocks also.This open stock existed storage location should be relevant to MRP

    please specify the MRP type and planning strategy whichever you are using

    Regards,

    Venkatesh..

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.