can I get cost plan (planned cost) in S_ALR_87013558 OR S_ALR_87013560 report

Dear All,

I have a requirement where in i want to see the cost plan in S_ALR_87013558  or S_ALR_87013560 report.

I have already searched I did not get an appropriate solution , kindly let me know how to go about it .

Regards

Suvin.S

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    May 18, 2015 at 05:20 AM

    Dear Suvin

    You can use T code CJE0  and selct report 12KST1D Plan/Actual/Variance

    Regards

    Vijay Kumar Hebbal

    Add comment
    10|10000 characters needed characters exceeded

  • May 18, 2015 at 05:54 AM

    Hi Vijay,

    These are budget specific standard report were cost plan not showing, if you want to see cost plan.

    but if you want to include the cost plan column in these standard report then you have to make some changes in standard report with the help of report painter.

    rgds

    Add comment
    10|10000 characters needed characters exceeded

  • May 18, 2015 at 06:24 AM

    Hi,

    create form by copy of 12KST1A. and add element as below characteristics.

    Hope this will help you.

    thanks

    Sunil

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 28, 2015 at 12:07 PM

    Hi

    you can  copy the standard report S_ALR_87013558  or S_ALR_87013560 report. and add cost plan in Report painter and Create a Z report

    Regards

    vijay kumar hebbal