LTP Exclude Time for Plannig scenario -->20 Only

Dear all,

how to Exclude the Planned Delivery time & GR Processing time In Schedule agreement During LTP execution for Specific planning scenario (20).

Due to above consideration there is a date shift in order start date and finish date.

Is there any config ?

For example: Material : X (Procurement Key is E) PIR made for 100 nos on 13.05.2015 Type is (PD)

Material : Y (Procurement Key is F) which is procured from vendor ZZZZ Which is the immediate child of Matl X in BOM where Type is (PD)

Via T code : MS02 for planning scenario 20 for material X LTP is executed.

Planned Order generated for Material : X on 13.05.2015

But for Material Y Purchase requisition for Material : Y on 11.05.2015 for qty 100 nos to vendor ZZZZ

Because in Schedule agreement for Planned Delivery time is 2 days


Where strategy group is 10 for both materials X and Y.

Requirement :

Material Y Purchase requisition for Material : Y should on 13.05.2015 Itself.

Regards,

U.linganathan.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on May 13, 2015 at 04:31 PM

    Hello

    This is not possible on standard but you can use BAdI MD_MRP_PARAMETERS.

    BR
    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.