on 05-12-2015 4:03 PM
Dear colleagues,
I can create a Work Approval from WSR8 with a reference to the PM order, but that does not link my Work Approval to the PM order.
It should be possible to create Work Approval directly in IW32, but there is no such option on the screen.
What customizing should I check?
Thank you,
Paulo
Hi Paulo,
This is configuration issue.Please check WCVOR7 Table and uncheck Do Not Display.this will link WA to your IW32.
Hope this will resolve your issue.
Regards
Vivek Patil.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Did you ever fix this issue? I have the same exact problem and can't seem to figure it out.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Paulo,
Did you use WCM control key in Maintenance order operations.
Regards.
Swapnil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Paulo,
Between what is WSR8 and what are you trying to achieving it.
Have you Activated Work Approval for maintenance orders?
Plant Maintenance - Work Clearance Management - Approval - Activate WCM for maintenance orders.
Here you need to maintain permit relevant for WCM ?
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Terence,
I am following the scenario from the BP 888 document.
After creating a Work Order with assigned Permit I got a system status WCM and want to create a WAP from IW32.
The setting is like this:
YU_WCM | Work Clearance Permit | WA | 1 | WC Application |
Can it be that fields/tabs are hidden for the Order Type even though WCM is active?
Thanks,
Paulo
Hi Paulo,
The link is based on the setting you make in the approval configuration.
You should have created Permits - When you assign these permits in Plant Maintenance - Work Clearance Management - Approval - Activate WCM for maintenance orders.
When this permit is assigned to Work Order, this will make the link available in the work order. The button will be available in the status bar...
Regards
Terence
Hi Paulo,
Just check below, what was the setting made in your system
Work Clearance Management - Master Data - Architecture - Do Not Display Dialog Box for Assignments
Check whether you have hidden the dialogue box.
SAP Help : If you work with work permits, we recommend that you hide the dialog box for assigning work approvals.
Regards
Terence
Hi Terence,
In my IMG structure I do not have such activity under Architecture. All I have are:
Assistant for Model Selection
Assistant for Maintaining Additional Applications
Define Descriptions
Define Direct Processing Mode
Define Relations
Define Processing Mode for Relations
Define Processing Mode for Navigation
Thank you,
Paulo
Hi Maria,
your advice was absolutely correct. ;o) This setting is the recommened setting for WPM. The IMG activity is hidden because the corresponding business function is not activated. Thererfore Paulo cannot correct the settting.
If you call transaction SIMGH than you maintain the IMG by ignoring the switches. Than it is possible to correct the settings.
Regards, Uwe
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.