Intercompany golive transission

Hello All,

we will be going live with the new SAP rollout soon. i have a situation, where we already have NL in SAP and now we are rolling out for USA. SInce NL is already in SAP and they deliver goods to USA plant. during the golive for the orders which are already been created in SAP by NL and Delvery is been created and goods are on water. how shall i proceed with these kind of orders with the new setup when we golive with USA.

thanks in advance

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on May 18, 2015 at 03:54 PM

    two options:

    1. Keep the existing process untill all the deliveries are completed. No new sales order under this customer. - Block it for any new orders.

    2. Reverse the delivery and delete the sales order, recreate the intercompany orders.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.