COHV- Rescheduling Orders

Hi All,

We are using MTO Scenario,

Following parameter set for mass scheduling of Orders-

Backward Scheduling,

Set Date as 25.05.2015 in OrdFin Under Back ward Scheduling,

Following data maintained in Material Master -

In-house production 0 days

Planned Deliv. Time 0 days

GR Processing Time 0 days SchedMargin key 000

After execution, System update Scheduling End date as 24.05.2015 i.e. 1 day before in all cases. What would be the reason ?

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on May 11, 2015 at 11:48 AM

    Hello

    System will not use the in-house production time from the material master to schedule production orders. The routing will be exploded and the basic start date will be calculated from the time set for the operations.

    See this blog for more details:

    CRP Basic Settings Part 2 – Routing

    BR
    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.