on 05-11-2015 9:03 AM
Hi All,
We are using MTO Scenario,
Following parameter set for mass scheduling of Orders-
Backward Scheduling,
Set Date as 25.05.2015 in OrdFin Under Back ward Scheduling,
Following data maintained in Material Master -
In-house production 0 days | Planned Deliv. Time 0 days |
GR Processing Time 0 days | |
SchedMargin key | 000 |
After execution, System update Scheduling End date as 24.05.2015 i.e. 1 day before in all cases. What would be the reason ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Rahul,
I think this is standard behavior of the system if you notice end of of order is set to 24:00 on 19/5 so that it is available on next day i.e on 20/5.
See SAP Note 150007 - Consulting: Scheduling of production orders
With an in-house production time equal to 0 days, it is assumed that the material can be produced at any time of a day. For this reason, the order finish date is set to 24:00
BR
KK