COHV- Rescheduling Orders

former_member620323
Active Contributor
0 Kudos

Hi All,

We are using MTO Scenario,

Following parameter set for mass scheduling of Orders-

Backward Scheduling,

Set Date as 25.05.2015 in OrdFin Under Back ward Scheduling,

Following data maintained in Material Master -

In-house production  0   days        

Planned Deliv. Time  0   days

GR Processing Time   0   days        
SchedMargin key  000

After execution, System update Scheduling End date as 24.05.2015 i.e. 1 day before in all cases. What would be the reason ?

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

System will not use the in-house production time from the material master to schedule production orders. The routing will be exploded and the basic start date will be calculated from the time set for the operations.

See this blog for more details:

BR
Caetano

former_member620323
Active Contributor
0 Kudos

Hi Caetano,

When I am going to set 25.05.2015 or any date in OrdFin Under Back ward Scheduling, system updated as 1 day before i.e. 24.05.2015.

I couldn't find the reason..

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Is this issue happening for production or planned orders?

Did you already checked the dates/times of the routing operation?

I suggest you to read carefully the following notes:

152319Consulting: Scheduling of planned order for routing
156933

Consulting: Scheduling routing

BR
Caetano

former_member620323
Active Contributor
0 Kudos

Hi,

This issue is happening in Production Order execution.

In COHV, I set below date

& in production Order, system updates(19.05.2015) as shown below-

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Check if you are using night shifts on the work center operations.

BR
Caetano

kiran_kumar179
Active Contributor
0 Kudos

Rahul,

I think this is standard behavior of the system if you notice end of of order is set to 24:00 on 19/5 so that it is available on next day i.e on 20/5.

See SAP Note  150007 - Consulting: Scheduling of production orders

With an in-house production time equal to 0 days, it is assumed that the material can be produced at any time of a day. For this reason, the order finish date is set to 24:00

BR
KK

former_member620323
Active Contributor
0 Kudos

Hi,

No Shift Sequence has been maintained in Work Center.

former_member620323
Active Contributor
0 Kudos

Hi,

I have checked on other client its taking correct scheduling date that I mentioned while executing COHV.

Answers (0)