SAP APO tables of Scheduling offset, Scheduling value of PP/DS orders

Former Member
0 Kudos

Hi,

Please let me know where scheduling offset, scduling value of an planned order/ process orders is saved in SAP APO?

How can I update the above values for an existing process order in SAP APO - PP/DS?

Thank you in advance.

Regards,

Surajit Das

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Hi Surajit,

The scheduling offset is stored with the input and/or output details of the order, in the liveCache.

You may display the order details in the liveCache as per document below:

The scheduling offset for each i/o node can be seen in ET_INPUTS / ET_OUTPUTS, field OFFSET_VALUE.

A possibility to update the scheduling offset is to reexplode the existing orders. If the PDS contains the updated values, they will be updated in the order.

Best regards,

Tiago