Hi PS gurus,

Please assist me on one issues related with budget return here IM budget has interface with PS.We have done Budget Carry Forward from 2014 to 2015 by CJCO transaction. After some time business user has realized that this budget has no use in project and hence they want to return back the budget from project to position ID.I am using IM52 with return radio button budget return but system says

"No measures found

Message no. AP083"

I have used IM48 indeed and I am getting the same message from SAP system and budget is clearly showing in SAP report - S_ALR_87013558 - Budget/Actual/Commitmt/Rem.Plan/Assg

Please assist in here whether I am doing any thing wrong in here, waiting for your valuable suggestions

Regards

Ranjeet

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

4 Answers

  • Posted on May 08, 2015 at 05:17 AM

    Dear,

    Could you try with transactions to transfer and return the budget from one project to other project

    Return: CJ38 ,CJ35, and to Transfer CJ34.

    Regards,

    Pardhu

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      I agree. For returning budgets between project and from a project respectively, CJ38 and CJ35 should be used.

      However, where project budget has to be returned back to an IM Position then IM52 should be used.

      Thanks.

  • Posted on May 11, 2015 at 09:17 AM

    Hello,

    Check whether you have upload the budget in IMPS, is that IM30? if yes then remove figure from there if release budget functionality is not availing.

    IM38 return budget from object level.

    Regards,

    Sanjeev

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 14, 2015 at 08:35 AM

    Hi Ranjeet,

    "No measures found" error is received when one or more of the following conditions are NOT met:

    1. IM Position must be assigned to a measure / WBS element / order etc.
    2. IM Position Master Data: This must have the ‘Budget Distribution’ indicators checked.
    3. WBS Element Master Data: WBS element user or system status must support the budget distribution.

    Also, when you run IM52 (to return the budget) ensure that the Approval Year is still 2014. This is because, budget was originally distributed from the IM Program approved in year 2014 and then carried forward. Therefore, when performing the return you should use the same IM Program and the Approval Year.

    Let us know if this does not solve the issue.

    Thanks

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 18, 2015 at 05:45 AM

    Hi Ranjeet Gupta

    You can return budget by selecting Carry forward measures radio button and Process transaction as return

    Regards

    Vijay Kumar Hebbal

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.