Dear Gurus,

MRP is regenrating the planned order after the completely GR against the Production order.

e.g

Sales Order : 39

MRP type - PD

Lot Size - ZX (copy of FX)

Fixed lot size : 13

Strategy group : 25

Consumption mode : 4

bwd consumption per : 200

fwd consumption per : 200

Planned order generated : 3 (After MRP run) of 13 ton.

One planned order is converted to production order and Completely GR against the production order.After GR the stock is transferred to another material.

Planned order of 13 ton is generated again when MRP is executed.

Why this extra planned order is generated when we have already receive FG againt the sales order ?

Regards,

Sudarshan