Skip to Content

Planned Order History

Dear Experts,

I have query here that is there anyway to track the planned orders which has been converted to PR. I have tried many ways to get any link, but couldnt. So i am seeking your help.

The question arised in mind because our client is facing an issue that they could see the planned orders in system even after converting it to PR.

Can anybody tell me the reason for the above? Is there anyway to track those planned orders?

RG,

Arvind

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

4 Answers

  • May 05, 2015 at 11:05 AM

    Hello

    System does not save any kind of logs for the planned order.

    The planned order should be deleted from the system after the conversion to purchase requisitions or to productions orders.

    Maybe MRP is creating new planned orders after the conversion. It may happen if the purchase requisition is in the future, outside the rescheduling horizon or not included in the rescheduling check. In this case, you would see exception message 20 for the requisition on MD05.

    What is rescheduling and how does it work - ERP Manufacturing (PP) - SCN Wiki

    See this link for more details.

    BR
    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • May 05, 2015 at 01:44 PM

    Aravind,

    Please share MD04 snap shot for your scenario because as Caetano already mentioned already converted PRs might not be fulfilling the requirements for any of the reasons as mentioned so system is creating new planned orders.

    BR
    KK

    Add comment
    10|10000 characters needed characters exceeded

  • May 06, 2015 at 03:04 AM

    As far as I know, as soon as planned converted to PR, system clear the planned order tables. so nothing left behind to setup the link.

    Add comment
    10|10000 characters needed characters exceeded

  • May 07, 2015 at 07:11 AM

    Hi Experts!!

    Thanks for prompt reply.

    Yes.. It shouldnt happened. These Planned Orders are from APO SNP and CIFed to ECC. Here user is stick on ths issue and he is telling we could see the same planned orders in SNP even after converting this Planned order into PR.

    But I cant prove them that this is different planned order as we dont have any track on converted planned order.

    Thanks,

    Aravind S

    Add comment