May 04, 2015 at 09:33 AM

product costing

13 Views

Hi Experts,

we have a production order for a semi finished configurable material.Not all the materials are consummed for the order.

after doin confirmation when we check cost analysis, we are getting -ve value in actual cost(sum of the actual cost).

that is because some materials are not consummed.

we dint maintain std or mov price in mat master for header material,it is pickin the total plnd cost cost for the change in stock cost for sfg.

please suggest me in this case

weather if post variance ill get the actual cost for the sfg material