SAP QM Inprocess Inspection for a specific Process order type

Dear All,

There is a requirement. As no QM type is maintained for FG material in a plant. Now the requirement is there is a specific order type for which Inprocess Inspection  is to be activated for all the FG materials. But at the same tie for all other order types there won't be any inspection for the same set of FG material.

I tried creation Z03 by copying  03 inspection type. But the problem is source inspection is from Production. So Z03 is not confined to only the specific process order but instead it is generating inspection lot for other Process order also.

Is it possible to create a scenario where we can attach inprocess inspection to a specific order type only.

Regards,

Rahul

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • May 02, 2015 at 03:01 PM

    Hi,

    You can assign the in process inspection to Order type in SPRO as shown below in the process order type dependent parameters in Planning tab in COR4.

    Check and revert..

    Thanks

    Kumar

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hello Rahul,

      In order to generate inspection lot for production order, you need to maintain inspection type 03 (or 04 if you need to have the inspection lot after confirmation) at the material master QM view. This is a pre-requisite. Then the system will generate inspection lot for configured order types.

      Regards,

      Ayoub.

  • May 04, 2015 at 05:43 AM

    Hi Rahul, I don't see this is feasible in standard! You need to develop and apply some custom logic specifying conditions for order types using exit that governs the control on inspection lot generation. You can explore exit QPL10001 or QAAT0001 with ABAP.


    Anand

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear Anand,

      Actually it doesn't work for the standard so enhancement is required. Thank you for the solution.

      Regards,

      Rahul

  • avatar image
    Former Member
    May 04, 2015 at 06:21 AM

    Request for closure of thread.

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Rahul, you may close the thread from your end as the Original Poster has the option to close it.😊. Great to know that it is been concluded.! Thanks for confirming.

      Anand